RESOURCE CONSTRAINED SCHEDULING (P194) from Garey & Johnson, A5 SS10. A classical NP-complete scheduling problem where unit-length tasks must be assigned to identical processors under both a processor capacity limit and resource usage constraints per time slot. NP-complete in the strong sense even for r = 1 resource and m = 3 processors, established by reduction from 3-PARTITION [Garey and Johnson, 1975].
Associated rules:
R139: 3-Partition -> Resource Constrained Scheduling (this model is the target)
Definition
Name:ResourceConstrainedScheduling
Reference: Garey & Johnson, Computers and Intractability, A5 SS10
Mathematical definition:
INSTANCE: Set T of tasks, each having length l(t) = 1, number m in Z+ of processors, number r in Z+ of resources, resource bounds Bi, 1 <= i <= r, resource requirement Ri(t), 0 <= Ri(t) <= Bi, for each task t and resource i, and an overall deadline D in Z+.
QUESTION: Is there an m-processor schedule sigma for T that meets the overall deadline D and obeys the resource constraints, i.e., such that for all u >= 0, if S(u) is the set of all t in T for which sigma(t) <= u < sigma(t) + l(t), then for each resource i the sum of Ri(t) over all t in S(u) is at most Bi?
Variables
Count: n = |T| (one discrete variable per task, choosing the time slot in which it is scheduled)
Per-variable domain: {0, 1, ..., D-1} -- the time slot assigned to each task
Meaning: sigma(t) in {0, 1, ..., D-1} is the start time of task t. All tasks have unit length, so task t occupies time slot [sigma(t), sigma(t)+1). At each time slot u, at most m tasks can execute simultaneously, and the total requirement for each resource i must not exceed Bi.
Schema (data type)
Type name:ResourceConstrainedScheduling Variants: none (no type parameters; resource requirements and bounds are plain positive integers)
Field
Type
Description
num_tasks
usize
Number of unit-length tasks n =
num_processors
usize
Number of identical processors m
resource_bounds
Vec<u64>
Resource bound Bi for each resource i (length = r)
resource_requirements
Vec<Vec<u64>>
Ri(t) for each task t and resource i (n x r matrix)
deadline
u64
Overall deadline D
Complexity
Best known exact algorithm: NP-complete in the strong sense even for r = 1 and m = 3 [Garey and Johnson, 1975]. For fixed m, the problem is strongly NP-hard (no pseudo-polynomial algorithm unless P=NP). Exact approaches use branch-and-bound, integer programming (binary ILP: x_{t,u} in {0,1} indicating task t starts at time u), or constraint programming. For m = 2 with arbitrary r, the problem can be solved in polynomial time by matching. No known exact algorithm improves upon O*(D^n) brute-force enumeration for the general strongly NP-hard case.
Extra Remark
Full book text:
INSTANCE: Set T of tasks, each having length l(t) = 1, number m in Z+ of processors, number r in Z+ of resources, resource bounds Bi, 1 <= i <= r, resource requirement Ri(t), 0 <= Ri(t) <= Bi, for each task t and resource i, and an overall deadline D in Z+.
QUESTION: Is there an m-processor schedule sigma for T that meets the overall deadline D and obeys the resource constraints, i.e., such that for all u >= 0, if S(u) is the set of all t in T for which sigma(t) <= u < sigma(t) + l(t), then for each resource i the sum of Ri(t) over all t in S(u) is at most Bi?
Reference: [Garey and Johnson, 1975]. Transformation from 3-PARTITION.
Comment: NP-complete in the strong sense, even if r = 1 and m = 3. Can be solved in polynomial time by matching for m = 2 and r arbitrary. If a partial order < is added, the problem becomes NP-complete in the strong sense for r = 1, m = 2, and < a "forest." If each resource requirement is restricted to be either 0 or Bi, the problem is NP-complete for m = 2, r = 1, and < arbitrary [Ullman, 1976].
How to solve
It can be solved by (existing) bruteforce. (Enumerate all D^n assignments of tasks to time slots; check processor and resource constraints at each slot.)
It can be solved by reducing to integer programming. (Binary ILP: x_{t,u} in {0,1}, sum_u x_{t,u} = 1 for each t, sum_t x_{t,u} <= m for each u, sum_t Ri(t)*x_{t,u} <= Bi for each i,u.)
Other: For m = 2, solvable in polynomial time by bipartite matching.
Motivation
RESOURCE CONSTRAINED SCHEDULING (P194) from Garey & Johnson, A5 SS10. A classical NP-complete scheduling problem where unit-length tasks must be assigned to identical processors under both a processor capacity limit and resource usage constraints per time slot. NP-complete in the strong sense even for r = 1 resource and m = 3 processors, established by reduction from 3-PARTITION [Garey and Johnson, 1975].
Associated rules:
Definition
Name:
ResourceConstrainedSchedulingReference: Garey & Johnson, Computers and Intractability, A5 SS10
Mathematical definition:
INSTANCE: Set T of tasks, each having length l(t) = 1, number m in Z+ of processors, number r in Z+ of resources, resource bounds Bi, 1 <= i <= r, resource requirement Ri(t), 0 <= Ri(t) <= Bi, for each task t and resource i, and an overall deadline D in Z+.
QUESTION: Is there an m-processor schedule sigma for T that meets the overall deadline D and obeys the resource constraints, i.e., such that for all u >= 0, if S(u) is the set of all t in T for which sigma(t) <= u < sigma(t) + l(t), then for each resource i the sum of Ri(t) over all t in S(u) is at most Bi?
Variables
Schema (data type)
Type name:
ResourceConstrainedSchedulingVariants: none (no type parameters; resource requirements and bounds are plain positive integers)
num_tasksusizenum_processorsusizeresource_boundsVec<u64>resource_requirementsVec<Vec<u64>>deadlineu64Complexity
Extra Remark
Full book text:
INSTANCE: Set T of tasks, each having length l(t) = 1, number m in Z+ of processors, number r in Z+ of resources, resource bounds Bi, 1 <= i <= r, resource requirement Ri(t), 0 <= Ri(t) <= Bi, for each task t and resource i, and an overall deadline D in Z+.
QUESTION: Is there an m-processor schedule sigma for T that meets the overall deadline D and obeys the resource constraints, i.e., such that for all u >= 0, if S(u) is the set of all t in T for which sigma(t) <= u < sigma(t) + l(t), then for each resource i the sum of Ri(t) over all t in S(u) is at most Bi?
Reference: [Garey and Johnson, 1975]. Transformation from 3-PARTITION.
Comment: NP-complete in the strong sense, even if r = 1 and m = 3. Can be solved in polynomial time by matching for m = 2 and r arbitrary. If a partial order < is added, the problem becomes NP-complete in the strong sense for r = 1, m = 2, and < a "forest." If each resource requirement is restricted to be either 0 or Bi, the problem is NP-complete for m = 2, r = 1, and < arbitrary [Ullman, 1976].
How to solve
Example Instance
Input:
T = {t_1, t_2, t_3, t_4, t_5, t_6} (n = 6 unit-length tasks)
m = 3 processors, r = 1 resource, B_1 = 20, D = 2.
Resource requirements: R_1(t_1) = 6, R_1(t_2) = 7, R_1(t_3) = 7, R_1(t_4) = 6, R_1(t_5) = 8, R_1(t_6) = 6.
Feasible schedule:
Time slot 0: {t_1, t_2, t_3} -- 3 tasks <= 3 processors, resource usage = 6+7+7 = 20 <= 20.
Time slot 1: {t_4, t_5, t_6} -- 3 tasks <= 3 processors, resource usage = 6+8+6 = 20 <= 20.
Answer: YES -- a valid schedule meeting deadline D = 2 and resource bound B_1 = 20 exists.