SCHEDULING WITH INDIVIDUAL DEADLINES (P195) from Garey & Johnson, A5 SS11. A classical NP-complete scheduling problem where unit-length tasks with precedence constraints and individual deadlines must be assigned to m parallel processors so that every task meets its own deadline. The problem remains NP-complete even when the precedence order is an out-tree, but becomes polynomial for in-trees and for m = 2 with arbitrary precedence [Brucker, Garey, and Johnson, 1977].
Associated rules:
R140: Vertex Cover -> Scheduling with Individual Deadlines (this model is the target)
Definition
Name:SchedulingWithIndividualDeadlines
Reference: Garey & Johnson, Computers and Intractability, A5 SS11
Mathematical definition:
INSTANCE: Set T of tasks, each having length l(t) = 1, number m in Z+ of processors, partial order < on T, and for each task t in T a deadline d(t) in Z+.
QUESTION: Is there an m-processor schedule sigma for T that obeys the precedence constraints and meets all the deadlines, i.e., sigma(t) + l(t) <= d(t) for all t in T?
Variables
Count: n = |T| (one discrete variable per task, choosing the time slot in which it is scheduled)
Per-variable domain: {0, 1, ..., D_max - 1} where D_max = max_t d(t) -- the time slot assigned to each task
Meaning: sigma(t) in {0, ..., d(t)-1} is the start time of task t. Since all tasks have unit length, task t occupies [sigma(t), sigma(t)+1). The schedule must satisfy: (1) at most m tasks per time slot, (2) if t < t' then sigma(t) + 1 <= sigma(t'), and (3) sigma(t) + 1 <= d(t) for every task t.
Schema (data type)
Type name:SchedulingWithIndividualDeadlines Variants: none (no type parameters; all tasks have unit length)
Field
Type
Description
num_tasks
usize
Number of unit-length tasks n =
num_processors
usize
Number of identical processors m
precedences
Vec<(usize, usize)>
Edges (i, j) of the precedence DAG: task i must precede j
deadlines
Vec<u64>
Individual deadline d(t) for each task t
Complexity
Best known exact algorithm: NP-complete by reduction from VERTEX COVER [Brucker, Garey, and Johnson, 1977]. Remains NP-complete even if the precedence order is an out-tree. Solvable in polynomial time when: (a) m = 2 and precedence is arbitrary [Garey and Johnson, 1976c], (b) precedence is an in-tree, or (c) precedence is empty (solvable by matching for arbitrary m). For the general NP-complete case, no known exact algorithm improves upon O*(D_max^n) brute-force enumeration; practical solvers use branch-and-bound or ILP formulations.
Extra Remark
Full book text:
INSTANCE: Set T of tasks, each having length l(t) = 1, number m in Z+ of processors, partial order < on T, and for each task t in T a deadline d(t) in Z+.
QUESTION: Is there an m-processor schedule sigma for T that obeys the precedence constraints and meets all the deadlines, i.e., sigma(t) + l(t) <= d(t) for all t in T?
Reference: [Brucker, Garey, and Johnson, 1977]. Transformation from VERTEX COVER.
Comment: Remains NP-complete even if < is an "out-tree" partial order (no task has more than one immediate predecessor), but can be solved in polynomial time if < is an "in-tree" partial order (no task has more than one immediate successor). Solvable in polynomial time if m = 2 and < is arbitrary [Garey and Johnson, 1976c], even if individual release times are included [Garey and Johnson, 1977b]. For < empty, can be solved in polynomial time by matching for m arbitrary, even with release times and with a single resource having 0-1 valued requirements [Blazewicz, 1977b], [Blazewicz, 1978].
How to solve
It can be solved by (existing) bruteforce. (Enumerate all assignments of tasks to time slots, checking precedence, processor capacity, and deadlines.)
It can be solved by reducing to integer programming. (Binary ILP: x_{t,u} in {0,1}, sum_u x_{t,u} = 1 for each t, sum_t x_{t,u} <= m for each u, x_{t,u} = 0 for u >= d(t), and precedence constraints.)
Other: Polynomial for m = 2 (Garey-Johnson algorithm); polynomial for in-tree precedence.
Motivation
SCHEDULING WITH INDIVIDUAL DEADLINES (P195) from Garey & Johnson, A5 SS11. A classical NP-complete scheduling problem where unit-length tasks with precedence constraints and individual deadlines must be assigned to m parallel processors so that every task meets its own deadline. The problem remains NP-complete even when the precedence order is an out-tree, but becomes polynomial for in-trees and for m = 2 with arbitrary precedence [Brucker, Garey, and Johnson, 1977].
Associated rules:
Definition
Name:
SchedulingWithIndividualDeadlinesReference: Garey & Johnson, Computers and Intractability, A5 SS11
Mathematical definition:
INSTANCE: Set T of tasks, each having length l(t) = 1, number m in Z+ of processors, partial order < on T, and for each task t in T a deadline d(t) in Z+.
QUESTION: Is there an m-processor schedule sigma for T that obeys the precedence constraints and meets all the deadlines, i.e., sigma(t) + l(t) <= d(t) for all t in T?
Variables
Schema (data type)
Type name:
SchedulingWithIndividualDeadlinesVariants: none (no type parameters; all tasks have unit length)
num_tasksusizenum_processorsusizeprecedencesVec<(usize, usize)>deadlinesVec<u64>Complexity
Extra Remark
Full book text:
INSTANCE: Set T of tasks, each having length l(t) = 1, number m in Z+ of processors, partial order < on T, and for each task t in T a deadline d(t) in Z+.
QUESTION: Is there an m-processor schedule sigma for T that obeys the precedence constraints and meets all the deadlines, i.e., sigma(t) + l(t) <= d(t) for all t in T?
Reference: [Brucker, Garey, and Johnson, 1977]. Transformation from VERTEX COVER.
Comment: Remains NP-complete even if < is an "out-tree" partial order (no task has more than one immediate predecessor), but can be solved in polynomial time if < is an "in-tree" partial order (no task has more than one immediate successor). Solvable in polynomial time if m = 2 and < is arbitrary [Garey and Johnson, 1976c], even if individual release times are included [Garey and Johnson, 1977b]. For < empty, can be solved in polynomial time by matching for m arbitrary, even with release times and with a single resource having 0-1 valued requirements [Blazewicz, 1977b], [Blazewicz, 1978].
How to solve
Example Instance
Input:
T = {t_1, t_2, t_3, t_4, t_5, t_6, t_7} (n = 7 unit-length tasks)
m = 3 processors
Precedences: t_1 < t_4, t_2 < t_4, t_2 < t_5, t_3 < t_5, t_3 < t_6
Deadlines: d(t_1) = 2, d(t_2) = 1, d(t_3) = 2, d(t_4) = 2, d(t_5) = 3, d(t_6) = 3, d(t_7) = 2
Feasible schedule:
Time slot 0: {t_1, t_2, t_3} (3 tasks <= 3 processors; t_2 must finish by 1, so it starts at 0)
Time slot 1: {t_4, t_6, t_7} (3 tasks <= 3 processors; t_4 predecessors t_1,t_2 done; t_6 predecessor t_3 done; t_7 has no predecessors)
Time slot 2: {t_5} (1 task; predecessors t_2,t_3 done; d(t_5) = 3, finishes at 3 <= 3)
Check deadlines:
Answer: YES -- all tasks meet their individual deadlines.