docs(phase6) Scope 14 — complete retrospective with H-chain results#219

Draft
jkeeley2073 wants to merge 1 commit into
mainfrom
Dev-Phase7-Scope14
Draft

docs(phase6) Scope 14 — complete retrospective with H-chain results#219
jkeeley2073 wants to merge 1 commit into
mainfrom
Dev-Phase7-Scope14

Conversation

@jkeeley2073
Copy link
Copy Markdown
Contributor

Summary

Completes the Phase 6 retrospective (docs/build-spec.md § Phase 6 § Retrospective) with all H-chain outcomes, Scope 13 gate checklist results, and operational lessons from the 2026-05-14/15 execution sessions.

Opened as draft — merge when the three deferred Phase 7 gates pass:

  • Lighthouse CI thresholds met on live https://pinwiz.ai
  • axe-core zero WCAG AA violations on live https://pinwiz.ai
  • ≥ 30 days cost burn at or below $300/mo (~June 14)
  • User confirms Phase 6 exit and public launch

What's in this PR

  • Phase 6 status updated: 🟡 H-chain complete; 3 gates deferred to Phase 7
  • PR sequence extended to docs(phase6) Phase 6 retrospective, risk register update, gitignore fix #214feat(infra) Phase 7 A0 — Api ACA app, image tag params, deploy script #218
  • Deploy state: Deployment Stack + Cosmos Continuous Backup
  • H-chain outcomes with timestamps: H-Dash ✅, H-Alerts ✅ (all 5 fired), H-DR-Cosmos ✅ (~2 min restore), H-DR-Search ✅
  • Scope 13 gate checklist table — 14 rows, ✅/🟡/🔴 each
  • 6 additional operational lessons from the Phase 6 execution sessions (ARM null-access pattern, disableLocalAuth blocks v2/track, alert eval frequencies, Deployment Stacks rationale, Cosmos backup default, az cosmosdb restore flag)
  • [TBD] placeholders for launch date, 30-day burn, SLO baseline

To complete before merging

Fill in the TBD fields from Phase 7 once the deferred gates pass:

  • Launch date
  • 30-day cost burn snapshot
  • SLO baseline (first 30 days from App Insights workbook)
  • Lighthouse results
  • axe-core + NVDA results

🤖 Generated with Claude Code

Updates docs/build-spec.md § Phase 6 § Retrospective:
- Phase 6 status: 🟡 H-chain complete; 3 gates deferred to Phase 7
- PR sequence extended to include post-H-chain PRs (#214#218)
- Deploy state updated: Deployment Stack, Cosmos Continuous Backup
- H-chain outcomes: all 4 complete with timestamps and wall-clock times
  (H-Dash, H-Alerts all 5 fired, H-DR-Cosmos ~2 min, H-DR-Search validated)
- Scope 13 gate checklist: full table with ✅/🟡/🔴 per item
- Additional operational lessons 1–6 (ARM null access, disableLocalAuth,
  alert eval frequencies, Deployment Stacks, Cosmos backup, restore flags)
- Launch date / 30-day burn / SLO baseline: [TBD] placeholders for Phase 7
- Operational follow-ups updated (containerize app, DNS, OIDC, rate limiting)

Phase 6 closes when Phase 7 provisions the real app image, runs Lighthouse
and axe-core against https://pinwiz.ai, accumulates ≥30 days of cost burn,
and the user confirms public launch.
@jkeeley2073 jkeeley2073 added the claude-code Generated with Claude Code label May 15, 2026
@github-actions
Copy link
Copy Markdown

Code Coverage

Package Line Rate Branch Rate Complexity Health
PinballWizard.Application 88% 81% 1184
PinballWizard.Web 74% 72% 513
PinballWizard.Api 84% 73% 69
PinballWizard.Infrastructure 66% 67% 1856
PinballWizard.Core 77% 100% 62
Summary 74% (7602 / 10238) 73% (2455 / 3367) 3684

Minimum allowed line rate is 70%

Sign up for free to join this conversation on GitHub. Already have an account? Sign in to comment

Labels

claude-code Generated with Claude Code

Projects

None yet

Development

Successfully merging this pull request may close these issues.

1 participant